Milestone investment will infuse nearly $30 million into local economy
WENATCHEE, WA – Cranes and crews will raise the steel frame of Chelan PUD’s new Service Center this spring. The highly visible project is emblematic of major investments the utility is making to ensure long-term value, including hydropower modernization, fiber internet expansion and hardening the electrical grid for wildfire resiliency.
On Monday, Chelan PUD commissioners unanimously approved three resolutions authorizing the next phase of construction for the Service Center. With more than three-fourths of contracts awarded, the project is on track to stay within budget, $139.5 million
“This is an important moment in the district’s history,” Commissioner Randy Smith said after the Jan. 19 presentation to the board.
The PUD plans to award about $26.7 million in construction bids to local contractors and suppliers – including electrical, asphalt paving, landscaping and concrete supply. The Service Center project will also provide about $2.5 million in fees and taxes to the City of Wenatchee, Chelan County, and other junior taxing districts.
Staff also gave a progress report on the first construction phase – excavation and site work – which is on time and on budget. Since August, crews have been busy laying the underground utility and electrical work, and preparing the grounds for concrete foundations on the 19-acre campus. The grand opening is tentatively scheduled for early 2023.
The Service Center as an important investment for several reasons:
Service Center aside, most of Chelan PUD’s capital budget this year will be dedicated to other initiatives outlined in the 2020-2024 strategic plan, including: