CASHMERE — A long-term solution for restoring access to the Cashmere Boat Ramp could be completed in 2028, according to county officials.
The Cashmere Boat Ramp, which sits along a side channel of the Wenatchee River, primarily serves as an exit-point for one of the most popular Class III stretches of whitewater in the state.
Over the years, vegetation growth and accumulated sediment have increasingly obstructed flow into the side channel, prompting the county to seek out a long-term solution. After the December 2025 flood event deposited another 800-900 cubic yards of cobble into the channel, the need to find both a short- and long-term solution became more urgent.
“The Cashmere boat ramp is an extremely important asset to our community,” said Chelan County Natural Resources Senior Program Manager Erin McKay during a Nov. 10 community meeting. “However, the boat ramp is becoming dangerous and difficult to utilize.”
The long-term fix intends to serve both recreation and restoration needs. Restoring hydraulic flow to the side channel would not only create a safer and more reliable access point, but would also restore critical habitat for protected spring Chinook and steelhead, according to the county.
According to the project’s grant application, work will include re-establishing the disconnected side channel entrance by reshaping the outside bar, installing boulder features to split flows and prevent future sediment buildup, and replanting native vegetation to stabilize the bank. It will also update the aging asphalt and concrete ramp, add flagstone steps to increase safety, and add boulder and riprap scour protection to withstand flood events.
The $573,000 project is on track to receive 90% funding through Recreation and Conservation Office (RCO) grants, with the other 10% coming from local monies.
In the meantime, the county, in partnership with the City of Cashmere, has been working on a short-term solution, which would move the flood-deposited cobble from the side channel and onto the adjacent island.
The project will cost approximately $50,000, which has been secured through contributions from the city, county and Chelan-Douglas Regional Port Authority. However, progress has been stalled by permitting challenges, particularly with the Army Corps of Engineers, according to McKay.
“It’s been incredibly frustrating for us…We don’t understand why,” said McKay.
Taylor Caldwell: 509-433-7276 or taylor@ward.media